Contract to power
30–45
Days to installed
Solar. Design, permits, the crew.
60–90
Days to making power
Solar. Utility dependent.
2–7
Days for a roof or heat pump
No utility in the loop.
Design and site survey
Week 1
Someone measures the roof, the service panel and the load. This is where a proposal drawn off a satellite photo meets reality.
Permits and the utility application
Weeks 2–5
Your town issues the building and electrical permits; the interconnection application goes to the utility. Both queues are outside anyone's control.
Installation
A day or two
The visible part, and the shortest. A roof or a heat pump on its own finishes here — there is no utility step.
Inspection, then permission to operate
Weeks 6–13
The town inspects, then the utility grants permission to operate. Until that letter arrives the system stays switched off, however finished it looks.